Property Notifications and Spalling Update



UNITS CURRENTLY UNDER REMODEL:
Unit 270

11/11 - 11/14: Frame Ceilings / Light / Exhaust Fans / Hammer Drilling / Moderate to Heavy Noise 
11/14 - 11/19:  Install Lighting / Electrical Work / Moderate Noise
Unit 824
11/1 - 11/14: Install Interior Doors and Shower Glass / Moderate Noise
11/14 - 11/21: Final Cleaning / Detailing

Unit 1011
11/1 - 11/12: Drywall / Tape / Smooth / Moderate Noise
11/14: AOAO to Inspect Sound Membrane
11/15 -1 1/22: Tile Saw Cutting / Moderate to Heavy Noise
Unit 1113
11/7 - 11/8: Flooring Installation / Moderate Noise
11/12: Install Wood Baseboards and Blinds / Moderate
11/13: Paint Baseboards and Walls / Quiet Work
11/14: Final Cleaning and Detailing and Final AOAO Inspection / Light Noise


 

Spalling and Painting Project - Tower 1
August 2024 thru March 31, 2025

 
Units in Tower 2 will not be affected. However there will be scaffolding in various locations around
Tower 1.  Work hours are Monday - Friday 8am - 5:30pm, and weekends if needed. There will be no noisy work during the Holiday Period of December 21 thru January 3. There may be quiet work, but should not be disruptive.

On the schedule below, "Stack" refers to the last 2 digits of the room number being worked on.
Example: unit #1102 is shown as 02 on the schedule below, #813 is listed as 13, etc:

 





Examples of Scaffolding and Work:



Inside view of lanai wrapping for units being worked on: